The installation and removal of scaffoldings shall be carried out in a certain order. Some people think that the installation needs to be carried out in order, but it doesn't matter when it is removed. But it can't be removed at will. The removal of scaffolding also needs to follow the order. Only by mastering the removal sequence of scaffolding can we yield twice the result with half the effort.


Removal sequence:

(1) Remove the top handrail and railing column from the straddle first, then remove the scaffolding board (or horizontal frame) and escalator section, and then remove the horizontal bar, reinforcement bar and diagonal bracing.

(2) Remove the cross bracing from the top span, and simultaneously remove the top brace wall connecting rod and the top door frame.

(3) Continue to remove the second step gantry and accessories synchronously. The free cantilever height of scaffolding shall not exceed three steps, otherwise temporary tie shall be added.

(4) Continuously and synchronously remove. For the wall connecting rod, long horizontal bar and cross bracing, they can only be removed after the scaffold is removed to the relevant span gantry.

(5) Remove the sweeping bar, the bottom door frame and the sealing rod.

(6) Remove the base and take the base plate and heel block away.

  • Construction Precautions for Steel Formwork for Column

    Construction Precautions for Steel Formwork for Column

    Inspection of Steel Formwork for ColumnCarefully inspect the quality of the steel formwork used for columns. Check if the surface of the steel formwork is smooth and flat, without cracks, sand holes, ...
  • Formworks for Column: Construction Standards

    Formworks for Column: Construction Standards

    The construction standards for formworks for column primarily include the following aspects:Preparation for Formwork ConstructionEnsure that the formwork construction plan and formwork scheduling plan...
  • Use of Steel Formwork for Column

    Use of Steel Formwork for Column

    Features of Steel Formwork for ColumnSteel formwork for column is made from sturdy industrial steel plates. Due to the durability of the steel material, it is widely used in the construction of bridge...